CASE STUDY #105:
CARMEL CONDOS

 

“This was a high end condominium in Carmel, Indiana. The condensers were on the roof
and there was on unit on each floor and one for the common area.”

Project Details:
  • Completion: January 1, 2024
  • Location: Carmel, Indiana
  • Project Type: Condominium Complex
  • Size:
  • Application: Split
  • Contractor: R.T. Moore
  • Supplier Rep: Top Marketing, Inc.
The Challenges:
  • Long line set length requiring brazing multiple lines together.
  • Multi-story building required difficult bending around joists.
  • Installation in tightly spaced area.
The Solutions:
  • 300′ coils of Python from the roof down to the units.
  • Able to install end to end with one piece down 5 stories.
  • Making tight bends much easier than copper.
The Benefits:
  • No brazing!
  • No joints inside wall cavities.
  • Less kinking within the structure.

DOWNLOAD PDF: Click Here